Erik Paulson wrote:
On Wed, Feb 09, 2005 at 03:36:40PM -0600, Gary Stiehr wrote:
Hello,
We have a cluster running the following condor version:
# condor_version
$CondorVersion: 6.6.6 Jul 26 2004 $
$CondorPlatform: I386-LINUX_RH72 $
We are interested in draining the jobs from just one node so that we can
perform maintenance on it. That is, we would like to allow the
currently running jobs to finish but to not allow any further jobs to
start on this node. Is there a way to do that in this version of
condor?
Set START=FALSE. No new jobs will be admitted to the execute machine.
Thanks, I will try that out. I can see that it would clearly keep new
jobs from being scheduled for this node. However, would this cause
existing jobs to be suspended or vacated once a condor_reconfig is done?
Thanks,
Gary
|