[Condor-users] draining jobs from only one node


Date: Wed, 09 Feb 2005 15:36:40 -0600
From: Gary Stiehr <stiehr@xxxxxxxx>
Subject: [Condor-users] draining jobs from only one node
Hello,

We have a cluster running the following condor version:

# condor_version
$CondorVersion: 6.6.6 Jul 26 2004 $
$CondorPlatform: I386-LINUX_RH72 $


We are interested in draining the jobs from just one node so that we can perform maintenance on it. That is, we would like to allow the currently running jobs to finish but to not allow any further jobs to start on this node. Is there a way to do that in this version of condor? What would happen if the condor_startd process was killed on a particular node? Would the condor_starter processes on that node continue to run until the associated jobs finished?


Thanks,
Gary Stiehr

[← Prev in Thread] Current Thread [Next in Thread→]