dag2:
JOB testD testD.sub
JOB testE testE.sub
JOB testF testF.sub
PARENT testD testE CHILD testF
But the result is: the executor will
always execute testA,testB,testD,testE,and then testC,testF, it is not
what I want. I need condor first finish dag1,then dag2,not like first all
parent jobs testA,testB,testD,testE, then child jobs testC,testF, does
anyone have this kind of problem? How can I solve this problem?
Thank you in advance!