HTCondor Project List Archives



[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: [Condor-devel] Feedback: Quill stress testing



On 10/18/05, Ian Chesal <ICHESAL@xxxxxxxxxx> wrote:
> seconds. It's when we remove large numbers of jobs that the quill binary
> really doesn't do well.
>
> If I submit 300 1000-job clusters and then condor_rm all 300 clusters with
> one command line the database grinds to a halt.

On a side note I should point out the same thing* happens to many of
my users when removing large numbers of jobs wihout quill (even if
those jobs aren't even running and are on hold!)

the condor_rm process in general seems seriously expensive

Matt

* takes ages - schedd stops responding, ends needing a net stop condor
to sort it out