On 06/20/2011 05:24 AM, Horvátth Szabolcs wrote:
Hi,

Is it possible setting/updating concurrency limits of running jobs?
It looks that if a job already started before setting the limits than it
is not considered.

Cheers,
Szabolcs
You cannot change the concurrency limits of running jobs. You would have 
to hold + change + release.
You can set limits at the same time you submit, so your second sentence 
is a bit odd.