On Wed, May 10, 2006 at 06:25:21PM -0400, Armen Babikyan wrote:
> Hi Erik,
>
> Thanks! Autoclustering was indeed the problem. Replacing
> "MY_RESOURCE_1" with "MY_RESOURCE_1 == TRUE" didn't solve the problem,
> but forcing the negotiator to consider all jobs with
> "NEGOTIATE_ALL_JOBS_IN_CLUSTER = true" did.
>
OK. You'll want to get rid of the NEGOTIATE_ALL_JOBS_IN_CLUSTER when 6.8.0 comes
around, we'll have fixed the problem with autoclustering by then (it might already
be fixed for 6.7.19)
-Erik