Mailing List Archives
Authenticated access
|
|
|
[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
[Condor-users] Jobs fail to start.
- Date: Wed, 29 Mar 2006 23:02:04 +0800
- From: "Sameer Bahl" <sameer.bahl@xxxxxxxxx>
- Subject: [Condor-users] Jobs fail to start.
Hi Everyone,
I was able to execute jobs on my condor (pool which consists of linux based central manager and windows based execute machines) till a few days back. However the same suddenly job fails to start now.
The following is the the output of condor_q -analyze command:
365.001: Run analysis summary. Of 8 machines,
8 match but reject the job for unknown reasons
0 match but will not currently preempt their existing job
0 are available to run your job
The sched log gives an error saying that the "gridmanager is way too old". I believe that the files are not being transeferred from the central manager to the execute machines. Howwever I am unable to figure out why.
Any help would be appreciated.
Thanks.
Sameer